A BOM has got several lines, one or more with negative quantity. Assumed, there is nothing on hand and a sales order for this BOM exists. Then Master scheduling creates a planned production order but it doesn’t calculate the negative lines as receipt.   MRP is calculating demands. Negative lines have no demand, no need to cover...

Read more

You want to firm several planned production orders with same start date. A certain work center (e.g. Lathe-1) is used in every route. The firmed production orders got scheduled with different start dates. Verify if the capacity is overloaded. If yes, job scheduling tries to schedule back and forth and back and forth until loop...

Read more